After the house was destroyed on Friday, the tree guys came on Saturday.

First, they had to remove some branches from the oak tree so that they would not fall on the new house.

On Monday they put in the footings. The temperature was around 25° but these guys acted like it was a bright summer day.

On Tuesday they built the crawlspace walls. The temperature was about 22° but they had a torch.

They started at 8:30 am and were done by 2:30 pm

Now we have a crawlspace. Next week they will start putting wood on top of it.

Then they backfilled the crawlspace and put in the new septic system